Tāmaki Precinct – Regeneration Projects
CLIENT:
Tāmaki Precinct 2A – Construction due to begin October 2021.
Tāmaki Precinct 2B – Project completed September 2021.
Tāmaki Precinct Torino – On-going, due for completion December 2021.
Available on request
This series of projects in Tāmaki is part of an over-arching urban regeneration programme being carried out in East Auckland.
The three projects were funded as a partnership between Kāinga Ora and the Tāmaki Redevelopment Company.
Cuesko was engaged to provide full post-contract services for each separate project including:
• Payment claim reviews and recommendations
• Variation assessments
• Financial reporting
Tāmaki Precinct 2A and 2B consists of 100+ individual units, including 2 and 3-bedroom multi-story terraced houses and extensive landscaping.
Tāmaki Precinct Torino is a development of 11 houses in four separate terraced blocks. The houses ranged from single to two-story.