Menu
Auckland : 09 477 4880 | Northland : 09 777 0941 | Tauranga : 07 777 0388

Fuel System Feasibility Study

Auckland International Airport Limited / WorleyParsons

CLIENT:

Auckland International Airport Limited / WorleyParsons
COMPLETION:

(Planned)
Phase 1 December 2021
Phase 2 January 2025
Phase 3 January 2027
Phase 4 December 2029
Phase 5 July 2040

REFERENCE:

Available on request

PROJECT DESCRIPTION

This long-term project involves the expansion of Auckland International Airport’s existing fuel supply network over a period of 23 years and create a resilient future-proofed ring-main system. It also involves the decommissioning and demolition of the existing tank farm and construction of a new facility.

It will be constructed in conjunction with other planned future airport expansion projects.

The project has several challenges that influence the construction, notably the airside works and associated restrictions.

The duration of this project requires a staged approach allowing for the airport to remain operational.

Cuesko’s were appointed by WorleyParsons to undertake feasibility cost estimating, projecting the total anticipated costs, staging the costs and isolating various sections of the project costs.