Auckland : 09 477 4880 | Northland : 09 777 0941 | Tauranga : 07 777 0388
MOE Schools (Te Waka Unua)
The Te Waka Unua School project consisted of two phases
CLIENT:
Ministry of Education
COMPLETION:
April 2017
REFERENCE:
Available on request
PROJECT DESCRIPTION
The Te Waka Unua School project consisted of two phases. Block One was constructed as part of the first phase. Phase Two consisted of renovations and extension to office area, sports hall, teaching block with open learning spaces, caretaker’s unit and extensive landscaping.
Cuesko were involved with the contract administration, processing payment claims and reviewing variations until final account stage.
A robust construction programme was provided and constantly monitored to avoid delays and problems were actively managed by the design team and contractor as a collaborate effort meaning the project was completed on programme.